Customer:
CAFC S.p.A.
Location:
Lignano Sabbiadoro (UD), Italy
Year:
2015
Technical description:
Construction and supply of no. 1 screw pump:
- capacity 500 l/s
- head 5,5 m
- power 45 kW
- screw diameter 1500 mm
- screw length 11300 mm
Extraordinary maintenance of:
- no. 2 screw pumps with capacity 200 l/s cad., head 3,5 m, power 11 kW
- no. 2 screw pumps with capacity 300 l/s cad., head 3,5 m, power 15 kW
Nominal characteristics
Total capacity plant: 1000 l/s
Head: 5,5 - 7,0 m
Total installed power: 97 kW
Particular notes
The Lignano wastewater treatment plant built in the '70s, collects the wastewater from the city of Lignano and carries out the treatment in order to return them purified to the community.
The intervention of Misa has allowed the reorganization of the initial lift, to guarantee the correct operation of the entire purification cycle.
Request information